When an RBCA Ceases Trading: What Happens Next?
31st October 2025

Last month we explained the need to undertake financial due diligence on your building control approver as Plimsoll Analysis had identified several that were likely to be taken over or at risk of financial failure. Unfortunately, this proved to be true and the sector has been shaken by the news this week of Assent Building Compliance (which also trades as Oculus and LB Building Control) ceasing to trade.
This has led to huge uncertainty for several projects and we have been flooded with enquires on what to do next. Unfortunately, there isn’t a simple answer to this as a series of legal and procedural crossroads emerge. However, this flow chart from the Association Of Building Control Approvers helps to show how projects transition and what responsibilities shift along the way.
Here we summarise the guidance as we currently see it (please note this is subject to change and we would recommend you take formal legal advice on your specific circumstances)
Have the works started on site?
Not Started
If not then the process is relatively simple and you can simply appoint a new RBCA (making sure you undertake due diligence), however this will mean you are still effectively paying twice for the service. Please get in touch if you require a quote.
Started
If the works have commenced then the process is more complex
Step 1: Determining the Status of the Initial Notice (IN)
The first question is whether the outgoing RBCA has issued a cancellation under Section 52(1)(a). Please check this with them and/or the Local Authority with great urgency. Ideally they haven’t, in which case the cancellation should then be issued by the person carrying out the work (this must match the person named on the initial notice), using form 10.
Step 2: Finding a new RBCA
The industry was already struggling with workload levels and as such finding a RBCA with capacity at the required project level will not be easy though we are working with several other RBCA’s to help channel people to those with relevant RBI’s e.g. Class 2A low rise domestic to 3G non-standard / non-HRB over 18m in height. We are focussing on commercial projects class 2D-3G as we have very limited capacity to take on domestic works.
Once the RBCA is appointed and the cancellation is validated, a new Initial Notice (IN) can be issued under Section 53(7)(b) — and importantly, this can happen without time limits and without a transfer report or certificate. However, the new notice must exactly replicate the description of work from the original IN to preserve continuity and compliance.
Step 3: Understanding Completion Status
It is also important to distinguish between incomplete and partially-complete projects, for example the RBCA may have issued (or be able to issue) a partial final certificate for some of the works – for example individual plots or the shell of a shell and core project, so please check if that has happened.
If a Partial Final Certificate has already been issued, the new RBCA is not responsible for the compliance of work covered by that certificate. If no certificate exists, the new RBCA assumes full responsibility for ensuring compliance across all work listed under the IN. This will require some form of due diligence check of the works completed to date by the RBCA and therefore there is no guarantee that they will be satisfied with the designs, the work completed to date or the records maintained by the outgoing RBCA.
Step 4: Time-Sensitive Transfers
If the notice is not cancelled using form 10 then a different rule applies, as cancellations under Sections 53(7)(a) and 53B (e.g. where the outgoing RBCA cancels the notice) are time sensitive. In those circumstances a new RBCA can only issue an IN within seven days of the original cancellation, accompanied by a transfer report / certificate submitted to the Local Authority. It is unlikely that a new RBCA will be in a position to quote, be appointed, and create a transfer report in that timescale given existing workload levels.
When timescales or procedural requirements are not met, projects are likely to revert to the Local Authority. This ensures that building control oversight is never left in limbo — safeguarding both public interest and the integrity of the regulatory process. However, given the scale of the number of expected reversions there is a risk of the Local Authority system becoming overwhelmed. As such both Public and Private sector RBI’s and support staff are currently doing everything we can to provide soft landings for as many affected clients as possible.
At Wilkinsons we are focussing on commercial projects class 2D-3G within London and the South East as we have very limited capacity to take on domestic works, or works outside of those areas (apart from fit out projects where we have some additional resource beyond our local area). If you are a domestic client, we would recommend contacting ABCA who will be able to match you up with another RBCA with capacity for domestic projects.