The Queue for The Loo Is Getting Shorter – It’s Time to “Part T”
16th May 2024

There was widespread coverage earlier this week of the laying of a law to require every new, non-residential building to have single-sex toilets, as well as a fully enclosed universal toilet if space allows. Behind the political posturing and electioneering what this actually means is that the Government have amended building regulations so that new offices, restaurants, hospitals and other non-residential buildings must have single-sex toilets. In addition to ssingle-sextoilets becoming the default, the associated guidelines will encourage the consideration of universal toilets, which are aully enclosed toilet rroomswith a wash hand basin for individual use.
During the consultation phase women, in particular, expressed concern about publicly accessible toilets being converted into gender-neutral facilities where users share cubicles and hand-washing facilities. This, they claimed, led to increased waiting in shared queues, decreased choice, and less privacy and dignity.
New Amendment Regulations have now been introduced to create a new functional requirement, T1, which states that toilet accommodation in buildings other than dwellings –
(a) must consist of-
- reasonable provision for male and female single-sex toilets, or –
- where space precludes provision of single-sex toilets, universal toilets, and
(b) may consist of universal toilets in addition to single-sex toilets.
The requirement means that you will now be expected to ensure
- Separate single-sex toilet facilities are provided. (NB Universal toilets can be provided in addition to single-sex provision and where space allows).
- All toilet accommodation must have clear and appropriate signage.
- Where space precludes single-sex toilet facilities from being provided, fully enclosed universal toilets should be provided.
NB There are several exemptions, such as dwellings, en-suite facilities in individual rooms for residential purposes and care homes, premises used for early years provision, schools, and cellular accommodation in custodial facilities.
In addition to the new Part T the Government have also amended Part G and Part M which also contain guidance on toilets. You can obtain copies of the new Approved Document and the revision booklets from the Download section of our website.
The new rules will apply from October 2024 and as usual there are transitional provisions in the legislation for projects where an application is submitted prior to the deadline.
Transitional provisions.
The new Regulations and Approved Document’s M do not apply where an initial notice has been given to the relevant authority in respect of that building before 1
October 2024, and the building work to which it relates has either
a. started and is sufficiently progressed before that date or
b. is started and is sufficiently progressed within the period of six months beginning of that date
For the purpose of these transitional arrangements, building work is to be regarded as ‘sufficiently progressed’:
a. where the building work consists of the construction of a building, when the pouring of concrete for the permanent placement of the trench, pad or raft foundations has started, or the permanent placement of piling has started; or
b. where the building work consists of work to an existing building when that work has started; or
c. where the building work consists of a material change of use of a building when work to effect that change of use has started.
Importantly, this definition differs from the 15% definition used elsewhere in the regulations.
It is important to recognise that any projects which haven’t already been submitted will require the appointment of a Principal Contractor in order to serve an Initial Notice. Additionally, even projects submitted a year or two years ago may require a redesign in accordance with the new Regulations if the works wont have sufficiently progressed by May 2025. Therefore, it is worth reviewing any projects that you are working on or have recently worked on to ensure that they wont be caught out by these changes.
If you are concerned how this will affect your project please reach out to one of our team who will be happy to help explain the changes.