Managing Non-Conformances During Construction
15th October 2025

In last month’s blog, we examined how we check plans and identify non-conformances in plan submissions: https://wilkinsoncc.co.uk/how-much-information-is-required/
This month, we’re looking at what happens when we identify issues on site.
1. Works Commenced Without Approved Plans
If works have commenced and we haven’t received the plans for checking; we have not received sufficient information, or we have identified non-compliance, we will send you an “at risk” letter along with the site report. As explained last month, works can continue, and the level of risk depends on what information is missing.
Lower Risk Scenarios: If we are requesting details of ventilation systems, M&E layouts, or internal finishes specifications, foundation work and external fabric construction can typically proceed without significant risk, as this information can be submitted later.
Higher Risk Scenarios: If we are requesting fire strategies that might affect layouts, structural calculations, or piling designs, groundworks and structural elements should not commence. Proceeding without approved layouts and structural solutions means working without formal building control approval for these critical elements, exposing all parties to significant compliance and safety risks.
2. Works Deviate from Approved Plans
If the contractor is not following the approved plans, this will be identified as a non-conformity in our site report cover letter.
Minor Deviations: Some changes are relatively minor, such as substituting one type of insulation for another approved product. In these cases, it’s simply a matter of revising the plans to ensure the correct information is recorded.
Significant Deviations: More substantial changes, such as making an extension larger or altering the number of flats being built, are much more significant. We will require a full set of revised plans and associated reports, including the fire strategy, heat loss calculations, structural designs, etc. It is likely that we will need to amend the Initial Notice, reconsult the fire service, and any approval to date may be nullified as a result.
3. Works Progressing Without Inspection
We appreciate that projects move at different paces and that circumstances can cause delays or interruptions. However, it’s important that you keep us informed about progress on a regular basis.
If we haven’t received an inspection request or update on your project for 60 days, we will write to you requesting an update on the progress of works. Please respond to this request with:
- A brief explanation of the current stage of works
- Geotagged photo(s) showing the current condition
This is essential as we must maintain active control of the project and verify, for example, that the building is not occupied without approval. Please do not ignore this request, as repeated unanswered emails will escalate to a threat to cancel (see below).
Important Timescales:
- If works have not commenced after 3 years, the project automatically expires and a new application is required
- In line with our terms and conditions, if works are not making reasonable progress and extend significantly beyond the originally agreed construction duration, we reserve the right to cancel the notice on the basis that works are no longer progressing.
4. Defective Work Identified
If the inspector identifies defective work—for example, a steel beam is the wrong size or a handrail to the stairs is missing—we will highlight this in the site report cover letter. It is essential that you respond and provide evidence that the works have been rectified. Sometimes this will simply require a geotagged photo; other times you may need to commission a report from your structural engineer or another professional to confirm they have checked the work and are satisfied.
Serious Contraventions: If the contravention is serious, we will serve a “90-day notice,” which is the period you have to resolve the issue (though see below regarding occupation). After this period expires, we will inform you that we are reverting the matter to the Local Authority to commence enforcement action. This is very much a last resort but unavoidable if you do not contact us and explain how you are resolving the issue.
5. Incomplete Work or Insufficient Evidence
This is very common, as it’s difficult to time inspections at the exact point when the contractor has completed the relevant works. The inspector may be satisfied with the work so far and doesn’t need to return but hasn’t seen all of the foundations, insulation, or drainage, for example. In these cases, we will request further photos of the remaining portions as they are completed.
It is important to provide this information to prevent issues later in the project. You will find these requests in the site report cover letter. If they are not resolved, they will roll over to the next inspection letter, and then the next, until we consider the need for formal enforcement action.
6. Work Covered Without Inspection
Sometimes the builder will have progressed and forgotten to request an inspection. In these cases, we will either ask for evidence that the work is correct or, in more serious cases, ask for the work to be exposed or opened up for inspection.
These requests are in the cover letter and MUST NOT be ignored. It is likely that this will escalate to more formal enforcement action if works continue without resolution.
7. Works Complete or Occupied
This is where matters become more formal. The legislation states that you only have a period of 4 weeks* from occupation or practical completion before your application expires and reverts to the Local Authority for enforcement.
Requesting an Extension: If you need more time to complete outstanding work, you may request an extension of time from the council, which we will arrange on your behalf. However, this is granted at the Council’s discretion and won’t be approved for serious issues such as missing fire doors or other key safety features. The maximum extension period is 3 months, although it may be possible to request a further extension for minor issues (e.g., if you are still waiting on delivery of a light fitting or for the contractor to send you a certificate or other document).
Important: The 4-week period “trumps” the 90-day notice mentioned above. For example, if there is a serious safety issue such as missing fire doors and we serve a 90-day notice, if you then occupy the building, the 90 days are reduced to a maximum of 28 days or the balance of the 90 days, whichever is less.
*Note: The 4-week period is extended to 8 weeks for projects that are not controlled under the Regulatory Reform (Fire Safety) Order, e.g., new houses or domestic extensions.
Key Takeaway:
Communication is critical throughout the construction process. Respond promptly to all correspondence, provide requested information and evidence, and keep us informed of progress. Early engagement with identified issues prevents escalation and ensures your project remains compliant and on track for a smooth handover at completion stage.