How much information is required?
15th September 2025

Following the publication of the Guidance Suite “Building Control Approval Application for a new Higher-Risk Building” by the Construction Leadership Council (CLC), we thought we would produce a guide to help understand the building control process for non-HRB projects.
The CLC guidance emphasises that applicants, should approach building control submissions with a sufficient level of design detail for Building Control Approval. Historical issues with the previous building control regime meant designs that were often lacking in detail to evidence compliance with the functional requirements of the Building Regulations 2010 (as amended), or to demonstrate that the completed design would be compliant.
The new building safety regime has brought a fundamental shift in the principles of the Building Control Approval application process. The principal designer role under the Building Regulations has fundamentally changed the expectations for design submissions. As the RIBA Practice Note emphasises, the principal designer must provide design work that is “suitable and sufficient to evidence compliance” with building regulations. This represents a significant shift from traditional practice where detailed compliance information might be developed later in the process.
Principal Designers Documentation
A critical misconception persists that planning permission drawings (typically RIBA Stage 3 level) provide sufficient detail for building control submissions. This is fundamentally incorrect under the new regulatory framework. Planning drawings, whilst adequate for demonstrating design intent and spatial arrangements, lack the technical detail necessary to evidence Building Regulations compliance.
Building control submissions now require RIBA Stage 4 (Technical Design) or Stage 5 (Construction) level detail packages. These must include comprehensive technical drawings, detailed specifications, performance calculations, and compliance statements that demonstrate exactly how regulatory requirements will be satisfied. Generic details, outline specifications, or drawings marked “details to be confirmed” are insufficient for modern building control assessment.
Principal Contractors Designs
Under the new framework, contractors and principal contractors must follow the design provided by the principal designer. This creates a direct dependency relationship where the quality and completeness of the initial design submission directly impacts the entire construction process. Insufficient or ambiguous design information at the outset can lead to compliance failures, programme delays, and potential safety risks.
The principal designer’s duty to “plan, manage and monitor” design compliance means they must demonstrate how Building Regulations compliance will be achieved before construction begins. This requires detailed consideration of technical solutions, material specifications, and construction methodologies at the design stage rather than leaving these critical decisions for later resolution on site. If the contractor continues to build without relevant information they risk taking on the role of a designer or even becoming the principal designer.
What we expect
When Wilkinson Construction Consultants are appointed as your building control body, we establish clear expectations from the outset. We require a minimum of RIBA Stage 4 drawings accompanied by a compliance statement that demonstrate’ s how Building Regulations requirements will be satisfied. This is not merely a preference but a professional necessity under the risk-based compliance assessment framework
What we do
Phase 1: Plan Assessment
The plan assessment phase forms the cornerstone of effective building control. During this stage, submitted plans, specifications, and supporting documentation undergo thorough scrutiny to identify potential compliance risks before construction begins. This desktop analysis serves as the primary risk assessment tool, establishing the framework for all subsequent control activities whilst optimising resource allocation.
Central to this evidence-based approach is the development of a tracker document that communicates identified risk areas to all parties involved in the construction process. This tracker serves as a live document that records:
- Specific compliance requirements identified during plan assessment
- Evidence required to demonstrate compliance for each risk area
- Methods for obtaining and verifying evidence
- Progress towards compliance verification
- Outstanding items requiring attention
Each tracker item represents a specific compliance risk that must be addressed through appropriate evidence gathering. Some items may be resolved through traditional site inspection, whilst others can be effectively discharged through alternative evidence such as photographs, calculations, specialist reports, or testing certificates.
Phase 2: Site Inspection
The site inspection phase involves the physical verification of construction work against the approved plans and building regulations. Many believe that this is the main part of the process, however, it’s essential to recognise that inspections represent just one tool within the broader toolkit available to RBIs operating under RBCA principles.
Modern building control practice acknowledges that physical site visits, whilst important, are not the sole means of gathering compliance evidence. The most effective approach combines targeted site inspections with other evidence-gathering methods to create a comprehensive compliance picture.
Under the Risk-Based Compliance Assessment framework, RBIs are only inspecting to satisfy themselves – not the duty holders – that works contain no contraventions, so far as reasonably practicable. This responsibility requires RBIs to adopt an inquisitive approach, actively questioning duty holders it is not and shouldn’t be considered as the clients primary route to demonstrating compliance.
As explained in the Manual to the Building Regulations, a RBI will not have checked every piece of building material and how it has been fitted or every aspect of submitted documents. It is the responsibility of those carrying out building work to comply with the Building Regulations, and to give a declaration of compliance at the end of the project.
For example, even if a building has received the final certificate or completion certificate, but the roof is leaking. The fact that the roof leaks is the Principal Contractor or Principal Designer’s problem and not the building control body’s problem.
The Tracker Document
Schedule A: Additional Information
As explained following our plan assessment, we produce a detailed tracker document that serves as the cornerstone of our building control process. Part A of this tracker constitutes our request for additional information that we consider essential design that is either incomplete or non-compliant. This section is normally the responsibility of the principal designer to address and represents items that must be added to the drawings or supporting documentation to achieve full compliance.

Schedule B: Testing and Commissioning Requirements
Schedule B of our tracker document contains all testing and commissioning items that must be discharged prior to gaining the final certificate upon project completion. These requirements are generally the responsibility of the Principal Contractor. Ideally you will not have appointed the contractor until you have received the tracker, and you can then ensure that they have priced for all the relevant testing and commissioning required.

Understanding Risk
It is crucial to understand that whilst construction works can commence before all Part A tracker items are complete, such works proceed entirely at the client’s and contractor’s risk. This concept operates similarly to planning conditions and should be managed with equivalent care and attention.
The nature of outstanding tracker items directly impacts which construction activities can safely proceed. For example:
- Low-Risk Scenarios: If we are requesting details of ventilation systems, M&E layouts, or internal finishes specifications, then foundation work and external fabric construction can typically proceed without significant risk, as the information on these systems can be submitted later.
- High-Risk Scenarios: If we are requesting fire strategies that might affect layouts or structural calculations or piling designs, ground works and structural elements should not commence. Proceeding without approved layouts and structural solutions means working without formal building control approval for these critical elements, exposing all parties to significant compliance and safety risks.
The tracker system enables informed decision-making about construction sequencing. Clients and contractors can assess which elements of work can proceed safely whilst other approvals are pending, and which elements must await specific approvals before commencement. This approach balances the need for project progress with regulatory compliance requirements.
Failure to properly sequence work in relation to outstanding approvals can result in non-compliant construction requiring costly remedial work, programme delays, and potential enforcement action. The tracker system provides transparency about these risks, enabling all parties to make informed decisions about construction timing and sequencing.
Avoiding Completion Delays
A fundamental principle of our process is that all Schedule A items must be completely discharged before practical completion can be achieved. This typically requires the submission of amended or additional drawings that address the outstanding compliance matters identified during plan assessment.
As a minimum requirement, even if detailed drawings are not yet available, responses must be provided in the designated response sections of the tracker document. These responses should clearly explain how each outstanding item will be addressed, providing sufficient detail to demonstrate that a compliant solution has been identified and will be implemented. If you are unable to edit a PDF please request a word or excel version.
Contractors should not leave site without providing all required Schedule B documentation. The consequences of this oversight are significant: without these certificates and test results, the final certificate cannot be issued, leaving the building legally incomplete regardless of its physical state. This can have serious implications for occupancy, insurance coverage, and warranty provisions.
Planning for Schedule B requirements should begin during the construction phase, with testing and commissioning activities scheduled well in advance of anticipated completion dates to allow time for any remedial work that may be required if initial test results do not meet specified performance standards.
Recommendations
- Front-loaded Design Development: Invest significantly more time and resource in developing comprehensive technical solutions during the design phase, ensuring all compliance pathways are clearly defined before submission.
- Enhanced Design Documentation: Provide detailed plans, specifications, and compliance statements that demonstrate how each Building Regulations requirement will be satisfied, including material specifications, construction details, and performance criteria.
- Early Specialist Integration: Engage specialist consultants and contractors during design development to ensure constructability and compliance solutions are thoroughly validated before submission.
- Systematic Compliance Mapping: Develop comprehensive compliance matrices that cross-reference every design element against applicable regulatory requirements, creating clear audit trails for building control assessment.
- Quality Assurance Systems: Implement robust design review processes that verify the completeness and accuracy of compliance information before formal submission, reducing the risk of later variations or compliance failures.
Conclusion
By understanding how plan assessment and site inspection phases complement each other within a broader evidence-based framework, construction professionals can better navigate the building control process whilst ensuring full regulatory compliance, and ensuring a smooth completion.
In next months Blog we will look at what happens when we identify a non-conformance on site during the building work.