The Grenfell Tower fire on the night of June 14, 2017, was one of the most devastating tragedies in modern UK history. 7 years on and the final inquiry report sets out the stark truth that every one of the 72 deaths were entirely avoidable.
Background
To understand how such a tragedy could occur, the government launched the Grenfell Tower Inquiry. The inquiry, split into two phases, sought to uncover the causes, assign accountability, and lay the foundation for stronger regulations to prevent similar disasters in the future.
The Phase 1 report, released in October 2019, focused on the events of the fire itself—how it started, how it spread, and the emergency response on the night of the disaster. This report drew a grim picture of systemic failure, pointing specifically to the use of flammable Aluminium Composite Material (ACM) cladding, inadequate fire safety measures, and confusion over evacuation protocols.
Phase 2 began in January 2020 with the objective of investigating the circumstances that allowed the tower to be in such a hazardous condition. This phase was significantly delayed due to the COVID-19 pandemic and other complexities in gathering evidence and testimony. Finally, after years of scrutiny, the Phase 2 report was published just a few days ago and set out several key recommendations.
DOWNLOAD SUMMARY OF RECOMMENDATIONS PDF
Who is to blame
One of the key questions the families of the victims wanted to know was who was to blame?

The report emphasizes that collective failure rather than individual wrongdoing was to blame. Each party, from architects to contractors, building control to regulatory bodies, contributed to an environment where safety concerns were overlooked or neglected.
Here’s a breakdown of those deemed most responsible:
1. Architects and Designers
The architectural team, specifically Studio E Architects, faced significant criticism for their failure to exercise proper care when selecting materials for the tower’s refurbishment, particularly the combustible cladding and insulation. Architects were also found to have a broader misunderstanding of building regulations, a problem that extends beyond just this case.
2. Contractors
The main contractor, Rydon, and other subcontractors such as Harley Facades, who installed the cladding, were heavily criticized for failing to take proper responsibility for fire safety during the refurbishment. There was poor communication between contractors, leading to confusion about who was responsible for ensuring the safety of materials and designs.
3. Building Control Bodies
The Royal Borough of Kensington and Chelsea (RBKC) Building Control, were faulted for insufficient oversight and the failure to appoint competent inspectors.
4. Fire Safety Consultants
The fire safety consultants, particularly Exova, were also identified as having failed in their duty to assess and advise on the fire risks presented by the refurbishment materials and design.
5. The Government and Regulatory Bodies
The UK government and regulatory agencies were found to have systemic failures in setting and enforcing fire safety regulations, particularly in high-rise buildings. The report highlights the lack of a national strategy for fire safety, ineffective building regulations, and years of ignored warnings about fire hazards. Previous fires, such as the Lakanal House fire in 2009, had exposed similar risks, but lessons were not learned, and critical reforms were delayed.
6. Manufacturers & Testing bodies
The manufacturers of the cladding and insulation materials, particularly Arconic (for the ACM cladding) and Celotex (for the insulation), were also named in the report. These companies supplied highly combustible materials, despite knowing the fire risks, and marketed them for use in high-rise buildings without appropriate warnings or restrictions. The Building Research Establishment (BRE), the National House Building Council (NHBC), and Local Authority Building Control (LABC) were heavily criticized for their roles in approving and certifying these construction products.
The Future
As we move into this new era of stricter regulations, everyone involved in building high-risk structures must remember the lessons learned from Grenfell and work towards creating a safer future for all.

However, it is not just high risk structures where the changes will be felt as we expect the recommendations to be implemented across all sectors and building types.
Geoff Wilkinson explains what this will mean for how building control will change.
“For years there has been an over reliance on Building Inspectors to be used as a source of advice and assistance, it was expected that we become part of the design team. Indeed that was how many in building control saw the role, one of advising how a proposal could be approved rather than simply responding -‘computer says no’. Unfortunately, that was exploited by the unscrupulous and many entering the industry forgot that the key function was to actually enforce the Building Regulations.”
The report has made it clear that this has to change and that Building Control will now solely be involved as a ‘regulatory’ function, not as an advisory or assistance function. The responsibility for understanding the Building Regulations is with the Principal Designer, Principal Contractor and the Client. This will not prevent us sign posting you to the relevant guidance, but will mean that we cannot answer questions in the way we have previously.
It will be down to the design team to clearly and accurately present their proposals to Building Control, ideally in the form of a compliance document. The RIBA have produced a Building Regulations compliance tracker for Architects to use to monitor that elements of design work comply with relevant Building Regulations. You will find Building Control Bodies require this to be submitted at plan check stage to evidence compliance with the requirements of regulations. RIBA members can access these documents via this link
We have also been told that we must not engage in design and that builders should refer any design questions or requests for product substitutions back to the Principal Designer. For small builders the FMB have produced this guide warning about becoming accidental designers and ensuring that any changes made are undertaken only by people with the necessary competency and qualifications.

Building Control have also been told to be less patient and tolerant of incomplete designs or poor quality work . As such designs should be submitted in full prior to works progressing on site, and that commissioning certificates must be produced promptly at the end of a project. A recent set of updated guidelines has made it clear that multiple extensions of time should not be agreed and that RBCA MUST now cancel Initial Notices and revert projects for enforcement.
The Future
Overall, responsibility needs to be held accountable, and as an industry, we need to become more technically competent and avoid corner-cutting for speed or costs.
At Wilkinsons, we are in an advantageous position as a long-standing, experienced, regulated Building Control Approver. Geoff Wilkinson, Managing Director of Wilkinsons, is registered and fully competent to deal with the most complex projects (Class 3 G & H), including Gateway 2 and higher-risk buildings.
To find out more why not come along to one of our CPD talks? Upcoming events include: