Gateway 2 for all projects from October?
12th May 2026 – by Geoff Wilkinson

As you may have spotted in last month’s newsletter, the government is consulting on the potential abolition of the Building Notice route and introducing building control plan approval requirements for all projects.
Background
This consultation didn’t emerge in a vacuum. It’s driven by two practical realities that MHCLG has identified through engagement with Building Inspectors and the emerging Building Safety Levy regime.
First, evidence from local authorities consistently shows that new dwellings regulated using building notices are more likely to require interventions to ensure compliance than those regulated using full plans approval. This reflects the simple principle that plans checking at the outset catches risks more efficiently than managing them through enhanced inspection schedules on site.
Second, and more strategically for the Government, the inability to charge the Building Safety Levy on building notice applications creates a perverse incentive: developers can avoid levy liability by electing not to submit plans for approval. Given that the Levy comes into effect on 1 October 2026, MHCLG is understandably concerned about an inadvertent rush towards the building notice route purely to sidestep a safety charge. This would fundamentally undermine both the Levy’s intent and the broader building safety reform agenda established by the Building Safety Act 2022.
The consultation focuses on four main areas
Mandatory Full Plans Applications
The headline proposal: all new dwellings using the LA route must be submitted as applications for building control approval with full plans. Building notices would no longer be an option for this work type.
The rationale is straightforward. Commercial projects already require a full plans application regardless of size, yet building notices remain an option for those using the LA system, despite the fact that new dwellings are honestly more complex than a simple shop fit. Plan checking at the outset allows registered building inspectors to verify that the proposed design meets the Building Regulations from the start of work. This is more efficient and more effective than discovering non-compliance through reactive inspections.
Importantly, MHCLG’s analysis suggests this won’t increase costs. In fact, it may reduce them. Why? The government is also consulting on whether this should extend to material alterations, extensions, loft conversions, and structural work, something we would strongly support.
Catching design problems before construction starts is always cheaper and easier than discovering them mid-build.
A project goes on site. Six weeks in, and we finally receive the structural design only to find that it doesn’t comply with current standards. Now the roof needs redesigning. Work stops. Everyone’s frustrated. Costs blow out.
Compare that to plans approval upfront. The same structural issue gets caught at design stage. The architect revises the design, gets approval, and work starts on time. No surprises, no need to stop work, no finger-pointing. No delays at completion stage trying to get the plans amended.
It’s not complicated. Approving plans before work starts just prevents problems and enables inspectors to have something to check against whilst on site.
Mandatory Plans Certificates
Currently, plans certificates are optional, given at a client’s request. MHCLG proposes making them mandatory for all new dwellings and Fire Safety Order buildings. The intent is that an RBCA cannot give a final certificate until a plans certificate has been given. This creates a “hard stop” ensuring that dwellings are built according to approved plans. It mirrors the LA route’s position where plans must be approved before work can lawfully commence (though practically, work can currently start two days after submission under LA regulations – a loophole that needs to close!)
There’s a sensible operational dimension here too. Some RBCAs are undertaking plans assessments too informally. Making this mandatory simply formalises existing best practice and creates consistency across the sector. However, the current wording that plans certificates can be given “with or prior to” final certificate stage still leaves another loophole. It could mean plans get approved before site work starts—which is ideal, or it could mean approval comes only at the final certificate stage, which is pretty useless. If you’re responding to the consultation, this gap is worth flagging. Mandatory plans approval before site commencement makes sense, and would bring in a gateway 2 for all projects.
If this does go ahead it’s important that plans certificates can be given “with requirements”, meaning an RBCA can set conditions for plan submission and additional package submissions at agreed stages, rather than requiring full approval before works can start on site.
Fire and Rescue Authority Consultation
Currently there’s a stark difference in the legislation. LAs only consult Fire and Rescue Authorities (FRAs) when reviewing full plans applications. However, as RBCAs we must consult on initial notices, amendment notices, plans certificates, and final certificate stages.
MHCLG proposes two options:
- Option A: Enhance LA requirements by requiring two FRA consultations (before/after completion certificate)
- Option B: Reduce RBCA requirements to initial notice only
We would like to see a third option that only requires consultation at the plan check stage – for example, before issuing a plan certificate.
Why this is good for Architects
Let’s be blunt. Some projects are designed by people who aren’t architects, don’t have architecture qualifications, and charge remarkably little for sketches. When building notice is available, there’s not much scrutiny of design quality. So cheap designs can make it onto site.
Mandatory plans approval changes that. Plans have to be submitted for building control review. They need to be proper, complete, defensible. A form of gateway 2 for all projects will mean a building control inspector can prevent this work from starting on site. Clients will learn: cheap (or non-existent) drawings mean rejections and delays. As a result architects doing proper work at proper fees should do better, not worse, in this environment, and therefore should support the proposal.
Why this is good for Builders
The requirement for full plans means that you are no longer expected to price off planning drawings with no detail, and your competitors should be pricing the same scheme as you. They can no longer get on site and sort details with the client as they go. You need a complete design before submission. When plans go to building control, they need to be sufficiently detailed. Structural calcs need to be there, specs need to be clear, drawings and details complete. That’s actually protection for you. The designer is taking responsibility for design, you are building to that design. If something goes wrong later, you can point to that, rather than arguing over who was responsible.
What Actually Happens Next
This consultation feels like it is being rushed as the proposals are tied to the Building Safety Levy’s commencement date (1 October 2026). In truth it has been on the cards for several years (if you have attended our CPD events you may well have heard us speak about it), however, it’s not until recently that the Government realised how it might affect the levy and means any legislative and procedural changes will need to be completed quickly between the consultation closing in June and the changes being implemented in October.
Therefore, it’s important to read and respond to this consultation as it marks potentially the most significant change in how projects operate and your future pipeline. We have seen how the poor implementation of gateway 2 to HRBs stalled the market, it’s essential that we don’t do the same to the entire sector.
For Architects:
- Respond to the consultation if you can. Support plans approval. Flag that small domestic work needs it most because that’s where compliance issues actually are. Highlight how this protects professional standards.
- Start thinking about your process for plans approval submissions. Good practices already do this, but it needs to be explicit now.
- Don’t position this to clients as a cost. Position it as protection.
For Builders:
- Respond if you can. Support it, but flag practical stuff: approval timelines, resource implications, whether October’s realistic for your business.
- Build proper time into project schedules for plans approval.
- Work with architects who understand plans approval requirements. Quality filter.
- Think about your own capacity. Can you handle projects where design is locked before site work starts?
Timeline
- Now to June: Consultation open.
- June – September: Government reviews feedback.
- October 1: New requirements in force.
Conclusion
Don’t ignore this consultation. It affects the entire sector, and should only take around 30 minutes to respond. After the BSR debacle the government is genuinely listening, and you know your business better than policy makers in Westminster.
It’s almost certain that major changes are coming in October and it’s better to shape them than react to them.
At WCCL, we’re preparing and publishing our formal response in the coming weeks. We’ll be flagging the approval timing gap and making the case for extending plans approval to material alterations, because that’s where compliance issues actually are. Plans approval before work starts is safer and cheaper overall. It protects architects from bad design undercutting. It protects builders from mid-project discovery of non-compliance. It protects clients from buildings that don’t actually comply.
Full consultation: gov.uk/government/consultations/plan-approval-requirements